- The work orders are displayed in sorted order based on "Priority Order"
- The Expected Date, Earliest Start Date or Priority Order Below columns can be changed or modified as required:
- Quantity
- Expected Date
- Earliest Start Date
- Priority Order
- Machine count
- Comments
- Additional Comments
- All the new work orders have status "NEW"
- User will have to change the status of a "NEW" work order to "OPEN" in order to schedule
- Once the work order is open, it can be released to allow production
- User can freeze/unlock any work order till the work order is started in production
- User can change the line of the work order
- User can close any work order as required
- After making changes in work order or priority, the work orders should be re-scheduled
- The work orders are color coded based on status. This color code can be defined as required
...