Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

There are two ways on how to set Source to multiple rows. 

From the Row Options screen

  1. Select row/s.
    Image Added
  2. Click on Options button. The Row Options screen will be opened. In the Source field select Units then click Ok.
    Image Added

  3. You will be back to the Row Designer screen. Now selected rows will have Units in the Source field.
    Image Added

From the grid 

Say you want to set these rows to have Units in the Source field. To do this follow the steps below.
Image Added

  1. Select row/s. Hold Ctrl key while clicking on the Source dropdown button of the first selected row.
    Image Added

  2. Select Column. Immediately the selected row/s will be updated with Column in the Source field.
    Image Added