This interface allows the user to define a set of rules/constraints, based on which Scheduling is done.

Rules Creation:

  1. Open Production Schedule Rules
  2. Select Holiday Type as 'Weekly'
  3. Tick a day
  4. Select the date range as shown in the below screenshot
  5. Click on Save button

General/Public Holiday Creation:

  1. Open Holiday Calendar
  2. Select Holiday Type as 'General/Public'
  3. Select the holiday date range
  4. Click on Save button

NOTE:

  • Holiday Type: 
    • Only one Holiday Type can be selected at a time.
    • Weekly Type specifies the repetitive non-working days of the week. E.g. Saturdays and Sundays.
    • General Type specifies holidays other than the weekly off. E.g. Labor Day, Thanksgiving Day.
  • Weekly Holidays: This frame is enabled only if Holiday Type is Weekly.