A DP (deferred price) contract will not allow entry of futures price, basis nor quantity.  Quantity will be incremented upon deliveries.

Here are the steps on how to add sequence:

  1.  Create a Contract Header
  2. At the time of creating contract header select Pricing Type as Priced 
  3. To add sequence, click on the Insert button.
  4. In the Contract Sequence screen enter the value in Details tab.
  5. Sequence No is system generated. It is non-editable.
  6. Status defaults to Open. Filed is not editable at the time of creation.
  7. Start Date defaults to Contract date. To change the date, click on the combo box button to open the mini calendar and select date. Default Start date can be configured at System manager → company configuration→ Contract Management
  8. To enter End Date, click on the combo box button to open the mini calendar and select date. Default End date can be configured at System manager → company configuration→ Contract Management
  9. To enter Event Start Date, click on the combo box button to open the mini calendar and select date. 
  10. To enter Planned Availability, click on the combo box button to open the mini calendar and select date. 
  11. To enter Updated Availability, click on the combo box button to open the mini calendar and select date. 
  12. The Location field is automatically filled in with the default Location set in the User configuration. To change it for a different location, select Location from combo box.
  13. The Item field is automatically filled in with the item configured for the location. To change item, select item from combo box.
  14. Origin
  15. To capture the Garden/Estate name, enterFarm ID.
  16. Enter Vendor Lot ID.
  17. Select the Container Type from the drop list.
  18. Enter the No of containers.
  19. The Quantity field is disabled.
  20. The UOM field is automatically filled in with the stock UOM set in the Inventory > Item option. To change it for a specific contract, select different UOM from combo box.
  21. Net Weight
  22. Original Quantity
  23. Unit/Layer
  24. Layer/Pallet
  25. Select Fixation By from the drop list.
  26. The Price Type field is disabled.

  27. No of Lots
  28. Select Market Zone from the drop list.
  29. Select Discount from the drop list.
  30. Select Storage Schedule from the drop list (this is required for a DP contract).
  31. Select Option from the drop list.
  32. In the Miscellaneous tab, click the Insert button to insert bag mark to the sequence.
  33. In the Contract Sequence screen enter the value in FX tab.
  34. Select the Invoice currency from the drop list.
  35. To enter FX Valid From, click on the combo box button to open the mini calendar and select date. 
  36. To enter FX Valid To, click on the combo box button to open the mini calendar and select date. 
  37. Select Currency Pair from the drop down.
  38. Provide valid Exchange Rate.
  39. Provide Multi line FX Remarks.
  40. Enter value for Assumed FX for Marginal Risk Report. 
  41. In the Contract Sequence screen enter the value in Miscellaneous tab.
  42. Select Pickup/ Delivery from the drop list.
  43. Select Transportation mode from the drop list.
  44. Select Book from the drop list.
  45. Select the Sub Book from the drop list. List will display sub books which are associated with the Book.
  46. Enter Farm Invoice No.
  47. Click on Insert button to insert certification to the sequence.

  48. Click on Save button.
  49. Sequence is added with Contract.
  50. To add another sequence click on the Insert button.

 

  • No labels